Jun 6, 2016 #1 gravel Geotechnical Joined Jan 29, 2003 Messages 19 Location US Where do you read off of, or obtain in program output, the total pond fill up-to-drainout dry time?
Jun 6, 2016 #2 psmart Active member Joined Feb 3, 1999 Messages 1,525 Location US The pond fill or draw-down time can be determined from the tabular hydrograph report, which has a column for elevation vs. time. For a graphical representation, right-click the hydrograph plot and select the "Elevation" curve. Peter Smart HydroCAD Software http://www.hydrocad.net Upvote 0 Downvote