Basin dewatering time increment

Status
Not open for further replies.

_mwill2023

Civil/Environmental
Joined
Dec 12, 2022
Messages
3
Location
US
Hi - i am new to hydrocad but trying to figure out how to add more time intervals to my hydrograph. I understand how to increase the time but not how to get smaller intervals. For example i am trying to show my mrcs basin dewaters in 192 hours but i cant figure out how to change the interval as my report only shows 190.00 and 195.00 hours.
mrc_time_ufppt8.png
 
The calculations are always performed at the exact time step (dt) that you specify on Settings/Calculation screen. However, a larger time interval is automatically used for the tables, in order to make them easier to read. If you release the "Shrink" button it will display more points.

Peter Smart
HydroCAD Software
 
thank you so much! that worked.
 