Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Basin dewatering time increment

Status
Not open for further replies.

_mwill2023

Civil/Environmental
Dec 12, 2022
3
Hi - i am new to hydrocad but trying to figure out how to add more time intervals to my hydrograph. I understand how to increase the time but not how to get smaller intervals. For example i am trying to show my mrcs basin dewaters in 192 hours but i cant figure out how to change the interval as my report only shows 190.00 and 195.00 hours.
mrc_time_ufppt8.png
 
Replies continue below

Recommended for you

The calculations are always performed at the exact time step (dt) that you specify on Settings/Calculation screen. However, a larger time interval is automatically used for the tables, in order to make them easier to read. If you release the "Shrink" button it will display more points.

Peter Smart
HydroCAD Software
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor