Where do you read off of, or obtain in program output, the total pond fill up-to-drainout dry time?
 
The pond fill or draw-down time can be determined from the tabular hydrograph report, which has a column for elevation vs. time.

For a graphical representation, right-click the hydrograph plot and select the "Elevation" curve.


Peter Smart
HydroCAD Software
 