Soils for Structural Fill
Soils for Structural Fill
(OP)
If a soil is classified as a poorly graded sand with gravel (< 3% fines and <29% gravel), will the soil be suitable for use as a structural fill.
How could an engineer assess the suitability of a soil for structural fill?
How could an engineer assess the suitability of a soil for structural fill?
RE: Soils for Structural Fill
enuff said.
RE: Soils for Structural Fill
Thank you for the answer. I would say that a granular dense material would be a good foundation.
But if the poorly graded sand with gravel (SPG) are imported materials, can they be compacted at site to a dense state without problems?
RE: Soils for Structural Fill
RE: Soils for Structural Fill
Most of the soils I deal with are SP. When a little gravel is thrown in, it's gravy!
RE: Soils for Structural Fill
I bring up a "test" that commonly is done on jobs, hand pushed rod penetration. If it hardly can be shoved in, it usually is good support. Try that in uniform sand and the rod will go in easily, but the stuff has a small range of density between loose and dense, thus a low potential for settlement, even if loose. Vibrate it and it is great stuff.
RE: Soils for Structural Fill
Also from a fieldwork point of view, is SP with about <5% silt content would pose problems for compaction with conventional compactors. I understood some have compacted SP materials satisfactorily with a plus minus 3% from Op moisture.
Now that the thread receives further attention, I would be interested if others may have similar experience? And how about compacting SPG materials.
RE: Soils for Structural Fill
Fine sands also tend to pump (build up excess pore pressure) if you are above optimum moisture. Be careful with that. Don't overkill on the compactor size either!
RE: Soils for Structural Fill
RE: Soils for Structural Fill
The fix was bring in a crane and lift the column up a little. Use a bulldozer and shove the footing off to the side. Excavate the uniform sand and backfill with a more well graded sand, compacted. Slide the footing back and re-set the column. Footing was about 7 x 7 ft. If you are careful, it can be done to as good as new.
Needless to say, to play it safe, lighter vibrating compactors on thin lifts were used thereafter.
RE: Soils for Structural Fill
You may have to specify the placement using relative density criteria. That means you'd need to run the tests for minimuma nd maximum void ratio. There's an astm standard for these tests.
compaction will be via vibration and density testing can still be via nuke gauge, but I'd run a few sand cone confirmations.
it's been a while though. . .
I'm sure if placed at 75 to 100 percent relative density, you'd have a good structural fill.
f-d
¡papá gordo ain’t no madre flaca!
RE: Soils for Structural Fill
RE: Soils for Structural Fill
RE: Soils for Structural Fill
I wonder if there is any other way that one could predict if the SP materials with 29% gravel (minus 1.5"), 68% (mainly medium) sand and 3% fines would be suitable for structural fill.
RE: Soils for Structural Fill
No one here is saying it is not suitable. The discussion is how to measure degree of compaction. In my footing case it was removed only because adjacent work was causing it to migrate when vibrated. If there was no nearby vibration,it would have stayed.
RE: Soils for Structural Fill
RE: Soils for Structural Fill
OK, if that is the case, I must have ok'd several hundred, maybe thousands of jobs with uniform sand as the structural fill DURING SOME 40 YEARS. Too late now I guess. Our main criteria to meet was no more than 5 % passing the No. 200 sieve for meeting frost requirements. GOSH For some reason no complaints or claims, Huh?
RE: Soils for Structural Fill
RE: Soils for Structural Fill
RE: Soils for Structural Fill
and oldestguy, I understand the poorly graded sand with gravel would be a suitable fill but its sustainability on water issues and confinement issues would be problematic. Is that right?
RE: Soils for Structural Fill
Your example, OG, appears to be an overzealous pump with no filtering to prevent removal of materials...thus the delta.
When we are dewatering a footing excavation, we require that pumping be done outside the footing from an adjacent sump. This allows the water to filter into the sump without disturbing the bearing soils of the footing. The same concept applies when you are trying to control groundwater under a building. It is imperative that the pumping process not remove material. This can be accomplished through a variety of preventive measures.