I don't know what more information is needed. Calculate the tension and supply enough steel to carry it. You may want to use a low steel stress to prevent excessive cracking in the concrete cover. Or perhaps you should use a post-tensioned tie.
If the load on the two branches of the 'Y' are a combination of dead and live load, you will need to analyze the column as a frame and consider unbalanced loads.
BA