Hi, I don't understand why list so many calendar: global, project, and resource. What the purpose of these terms ?
Sep 27, 2006 #2 Akhibi Mechanical Joined Sep 19, 2003 Messages 48 Location GB The Global calendar contains calendars that can be used by all projects are available for all resources and activities Project calendar Contains a separate calendar dedicated for each project and available for the current project only Greg Akhibi Clearwaters Consulting Ltd Upvote 0 Downvote
The Global calendar contains calendars that can be used by all projects are available for all resources and activities Project calendar Contains a separate calendar dedicated for each project and available for the current project only Greg Akhibi Clearwaters Consulting Ltd
Sep 27, 2006 Thread starter #3 7431 Petroleum Joined Feb 2, 2006 Messages 24 Location AU Thank you, Akhibi! Sometimes I am confused by so many different calendars. BTW, after the schedule finished in a project management team, the next step is print the plan and send to different engineers to review, or just submit to manager? Upvote 0 Downvote
Thank you, Akhibi! Sometimes I am confused by so many different calendars. BTW, after the schedule finished in a project management team, the next step is print the plan and send to different engineers to review, or just submit to manager?