I have a field situation. I need to weld two beams together at the flanges (one on top of the other). One flange is 7/16" and the other is 7/8".
This will be field welded with fillet welds along the seam between the flanges. Fillet welds will spaced not continuous.
Is there anything that needs to be done to get a good weld? Pre-heat?
This will be field welded with fillet welds along the seam between the flanges. Fillet welds will spaced not continuous.
Is there anything that needs to be done to get a good weld? Pre-heat?