It is always recommended that when tieing line pipe to the wellhead by welding the last wellhead 4130 flange weldneck to A106 grade B pipe, that the weld has to be pre-heated and post weld heat treated, preferably in the shop.
Is it possible to do this welding in the field without the heat treating and be fine or is should that recommendation be considered a requirement?
Of course this bothers on the chemistry and mech. properties of the 4130 being an unassigned material, not the 106B which is a P1 material.
Thanks you.
It is always recommended that when tieing line pipe to the wellhead by welding the last wellhead 4130 flange weldneck to A106 grade B pipe, that the weld has to be pre-heated and post weld heat treated, preferably in the shop.
Is it possible to do this welding in the field without the heat treating and be fine or is should that recommendation be considered a requirement?
Of course this bothers on the chemistry and mech. properties of the 4130 being an unassigned material, not the 106B which is a P1 material.
Thanks you.