Is there a code that states you cannot run water piping (Domestic or Fire) below a new building slab? I have a unique project where at the last minute, the city decided to change where the service could connect to the city main and it basically forced a design to run below the slab for about 50 feet and then turn up into a mechanical room. I was not able to find a code saying you cannot do this, although it's not the best practice to do. Our hands were tied unless the building were to be redesigned which at that stage was not feasible.
Now the contractor is spreading word that it's "illegal" and everyone is freaking out.
Now the contractor is spreading word that it's "illegal" and everyone is freaking out.