Volumetric examination in header nozzles weld

Status
Not open for further replies.

wayuu1981

Mechanical
Joined
Sep 15, 2006
Messages
47
Location
CO
Hello,

We are writing the technical specifications for contracting the replacement of secondary superheater panels and their connecting tubes to inlet and outlet headers in a 150 MW coal fired power plant.

Nozzle to header connections are similar to illustration z-1 in Figure PW-16.1. Header is SA-335-P11 12-3/4" OD x 2.143" MWT, and tubes are SA-213-T22 2" OD x 0.240" MWT.

Does these welds require RT or UT examination? or Volumetric examination of attachment welds may be omitted for this type of welds according to PW-16.3?

Thanks for your time, and any advice will be appreciated.



Javier Guevara E.
Projects, Mechanical Engineer
 
Hello

in my opinion, RT is not feasible/in-effective in this kind of joint. UT is partially feasible/effective, that too only with correct combination of angle probes. Still UT may be specified in the specification.
I would recommend MT in this type of weld.

Shashank
 