- Jul 6, 2022
- 501
I have a ridge than spans about 27.5 ft and 12.5 ft. I specified W14x48 and then (2)-LVL on the small span. The contractor wants to put steel beam the whole way (40 ft). He does not mind long heavy steel beam (unlike most residential contractor). When I analyze it as a continuous beam, I will have about -632 lb uplift with balanced load or -4262 lb uplift with unbalanced load. This is in the snow country. I am not sure I like this. My question is this. Is it possible to install the whole beam 40 ft long. Then next at the mid support you cut the top flange and bottom flange? That way the beam will still have continuous web but not flanges? Will that create a hinge to relieve the uplift? Or maybe just cut the top flange?