Hi, I am relatively new to Suretrack and am currently tasked with updating a monthly program. The original program was created on Primavera P3 and imported to suretrack for me to up date.

My understanding is that if I change the data date to the required date and then pres F9 to schedule the project then the project will automatically update and I can then adjust the individual tasks that require adjustment.

However when I schedule the revised program all the tasks are brought forward as id the data date was the new start date and everything is in the critical path as a result. Can anyone tell me what I am doing wrong?

Thanks in advance for any help you can give.