boffintech
Civil/Environmental
- Jul 29, 2005
- 469
Got a 10'x10' spread footing that needed to be undercut, over excavated in depth, to get down to suitable bearing material (rock).
Used 19yds3 of 4500psi concrete as backfill to get back up to bottom of ftg elevation.
The contractor wants to place the forms, the rebar, the column dowels, and then place the concrete for this foundation later today even though the flow-able fill was placed this morning. To speed up the flow-able fill set time a couple of bags of calcium chloride were used. No rebar was placed in the flow-able fill so no worries there...and this won't affect the rebar in the footing? Right?
Used 19yds3 of 4500psi concrete as backfill to get back up to bottom of ftg elevation.
The contractor wants to place the forms, the rebar, the column dowels, and then place the concrete for this foundation later today even though the flow-able fill was placed this morning. To speed up the flow-able fill set time a couple of bags of calcium chloride were used. No rebar was placed in the flow-able fill so no worries there...and this won't affect the rebar in the footing? Right?