bmoorthy
Mechanical
- May 29, 2003
- 457
In ASME Sec VIII Div 1, UCS 56 alternative longer soak time at lower temperature provision is given(Indicating that they are equivalent, although not explicitly). If a manufacturer opts to use this provision then is it necessary for the maufacturer to Perform PQT with longer soaking at lower temperature to support his WPS or is it OK if the normal cycle PQT would supports his WPS.