EngSD
Structural
- Dec 1, 2010
- 29
In the past I have found this forum extremely helpful as I have researched questions but this is the first time that I am posting my own question. The question pertains to an existing tunnel that will now be seeing additional load due to changes on a project(attached is sketch of the tunnel top slab and all the reinforcement). I have ran the analysis and the slab works for shear but the trouble I am having is with the flexure. The factored moment demand on the slab will be 69k-ft but analyzing the top slab as a 9' simply supported span and accounting only for the #8 bottom bars I only get a capacity of 53.5 k-ft (f'c=4,000psi and fy=60,000psi). My questions is whether or not the shear bars can be used to account for additional flexural reinforcement or if there is any other things I am not taking into account that would provide additional flexural support?
Thanks to everyone for helping.
Thanks to everyone for helping.