Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

tubesheet to shell butt weld joint radiography

Status
Not open for further replies.

Mech Engg

Mechanical
Aug 3, 2016
6
Dear Experts

We ordered one Double tubesheet exchanger to vendor. Both Tubesheets are welded to shell with Butt weld as per FIG UW-13.3.
Now as per vendor he cannot perform Radiography on this weld due to Tube hindrance and cannot perform UT due to 10 mm joint thickness.

he is suggesting PT.

What is your opinion pl
 
 http://files.engineering.com/getfile.aspx?folder=09141f02-79f8-4785-ab79-ea21554c53a9&file=Tubesheet_joint.png
Replies continue below

Recommended for you

Radiography is done prior to tube insertion so that should not be a problem.
 
Thanks All

Is this normal to weld all these tubesheets to shell on both side and then insert tubes one by one ?
there is no clear view how tube is travelling inside tubesheet until tit comes out from other side tubesheet
 
Our shop always completes these welds AFTER the bundle has been stuffed, exactly for the reason that you mention. Also, these welds do not require RT and/or UT.
 
Dear marty007
Thanks for your response, can you guide for code exemption if the exchanger is in Lethal service ? thanks in advance
 
Mech Engg
Why didn't you mention it before? (lethal service).
Another important data is comming from you?

Regards
r6155
 
Hi r6155
Sorry for late info, can you suggest any code exemption or provision of code cases or nay practical way of performing RT. Appreciated your time.
 
Refer UW-51(a)(4) of Code Section VIII-1-2015
As an alternative to the radiographic examination all welds in material 1/4 in. (6 mm)and greater in thickness may be examined using the ultrasonic(UT) method per the requirements of 7.5.5 of Section VIII, Division 2. Which is automatic or semi automatic recordable UT examination.

2017 edition words are different but intention is same (it refers to UW-53b that cross refers to 7.5.5 of VIII-2)

This method is acceptable for Lethal Service.

Probably TOFD and Phased Array combination will work. Talk to automated UT expert.
 
Dear sharmass
Thanks for your valuable input. It really helps.
So does it means all Tubesheet hub type connections with Shell in Lethal will be UT performed due to Tube Hindrance ? UW-2(a)(2&3) provides some waiver on inside Tube Butt joints and consider this is not possible to perform RT, then Why this Tubesheet to Shell Butt joint is also not included in this list of waiver. Just as thought to share.
 
I apologize, I didn't look clearly enough at your attachment. I had assumed it was a corner joint.

For your joint type, RT would be required (or UT per rules of ASME).

Cheers,
 
Thanks marty007
What is your opinon to perform RT on these joints, will you put all tubes after RT of Tubesheet to Shell weld ? is it Practical and normal to pass tubes after welding Tubesheet to shell from both ends ?
 
Do not give more laps with RT. Forget RT in this case. Use UT

Regards
r6155
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor