APHK
Electrical
- Mar 6, 2007
- 9
Hello to everyone this is my first post so as a little background I work for a medium sized electrical utility in Ontario Canada. I have been put in charge of building a new maintenance program for our substations and am in the process of collecting information.
We are starting with power transformers and are trying to build a schedule around testing and inspection. All of our transformers are liquid filled and range in secondary voltage from 4.16 to 44kv and primary voltage from 13.2 to 250kv
I have been looking at some books and documents but so far I have been reading through the second edition of Paul Gills Electrical Power Equipment Maintenance and Testing. It is a good reference but I wanted to see what other were doing and thought this may be a good place to pose the question.
So what kind of maintenance and testing schedule are you following for Power Transformers?
And what other books or references should I look into?
We are starting with power transformers and are trying to build a schedule around testing and inspection. All of our transformers are liquid filled and range in secondary voltage from 4.16 to 44kv and primary voltage from 13.2 to 250kv
I have been looking at some books and documents but so far I have been reading through the second edition of Paul Gills Electrical Power Equipment Maintenance and Testing. It is a good reference but I wanted to see what other were doing and thought this may be a good place to pose the question.
So what kind of maintenance and testing schedule are you following for Power Transformers?
And what other books or references should I look into?