engpes
Mechanical
- Feb 10, 2010
- 175
I have a unique situation where I have a C12x25 channel girder with later W8x35 beams tying in with steel floor plate on top (all welded / full MR connection). Typically this floor plate and W8x35 would tie in at the top flange (compression) giving the top compression flange effective lateral support.
In this particular case, the W8x35 and the floor plate are offset downward a few inches and do not tie in directly to the top (compression flange). I have always used the rule of thumb that as long as the entire C12x25 girder is prevented from twisting and that the girder is supported at least 2/3 of the way up its depth (W8 lateral beam), the top (compression flange) can be considered supported at that location.
My question is:
1.) Can this C12x25 girder compression flange be considered supported if the W8x35 lateral beam does not exactly line up with the top compression flange?
2.) Is there any section in AISC that addresses these actual requirements of compression flange bracing?
Thank you in advance.
In this particular case, the W8x35 and the floor plate are offset downward a few inches and do not tie in directly to the top (compression flange). I have always used the rule of thumb that as long as the entire C12x25 girder is prevented from twisting and that the girder is supported at least 2/3 of the way up its depth (W8 lateral beam), the top (compression flange) can be considered supported at that location.
My question is:
1.) Can this C12x25 girder compression flange be considered supported if the W8x35 lateral beam does not exactly line up with the top compression flange?
2.) Is there any section in AISC that addresses these actual requirements of compression flange bracing?
Thank you in advance.