bhiggins
Structural
- Oct 15, 2016
- 152
Hi all!
I'm working on a small 2 story concrete podium project. The structure is a conventionally reinforced moment frame supported on piers on top of a slab on grade with pier caps. The piers have been poured roughly 3 weeks ago and now the slab/pier caps are ready to be poured. The owner is behind on schedule and would like to pour the columns ASAP. I told him the standard time is 7 days for the slab to cure before the columns can be poured unless an accelerator is used. I cannot seem to find any guidance in ACI318 on the matter.
Can concrete cylinders be tested and reach a target concrete strength (possibly 50% f'c) for an OK?
We specify f'c=4,000 psi for the elevated slab and columns, what would be the target strength to take off the shoring for the elevated slab? If the slab is only roughly 1000 sqft, how many test cylinders are appropriate? This is a pseudo commercial project so we are doing a lot of the inspections ourselves.
I'm working on a small 2 story concrete podium project. The structure is a conventionally reinforced moment frame supported on piers on top of a slab on grade with pier caps. The piers have been poured roughly 3 weeks ago and now the slab/pier caps are ready to be poured. The owner is behind on schedule and would like to pour the columns ASAP. I told him the standard time is 7 days for the slab to cure before the columns can be poured unless an accelerator is used. I cannot seem to find any guidance in ACI318 on the matter.
Can concrete cylinders be tested and reach a target concrete strength (possibly 50% f'c) for an OK?
We specify f'c=4,000 psi for the elevated slab and columns, what would be the target strength to take off the shoring for the elevated slab? If the slab is only roughly 1000 sqft, how many test cylinders are appropriate? This is a pseudo commercial project so we are doing a lot of the inspections ourselves.