Irishkid
Computer
- Jun 15, 2008
- 2
Hello,
I am involved in a project with several other partners and am creating an ms project file to mapout my partivipation in the project. For example I have a task that has 3 subtasks. The task is scheduled to last 6 months. Of those 6 months my part will take 2 months split across the 3 sub tasks. So can I get the main task (summary task I think) to show 6 months for the duration and teh sub tasks to show various amounts adding up to 2 months?
Any help greatly appreciated. This is MS Project 2007
Thanks
I am involved in a project with several other partners and am creating an ms project file to mapout my partivipation in the project. For example I have a task that has 3 subtasks. The task is scheduled to last 6 months. Of those 6 months my part will take 2 months split across the 3 sub tasks. So can I get the main task (summary task I think) to show 6 months for the duration and teh sub tasks to show various amounts adding up to 2 months?