elambers
Civil/Environmental
- Nov 21, 2017
- 1
Hi,
First post ...
Using MS Project 2016
When I enter single day tasks (forecasted) they split across 2 days. On further investigation, it's because MSP changes the start time for these tasks to irregular times, such as 11:12 AM, then the 1 day task spans across 2-days.
Weird thing is; when you status the program - it often corrects to what it should be. . .
Checks I've done to try fix it:
- Calendar is 8AM - 5PM, no work 12:00 - 13:00 (lunch)
- Project Settings is 8AM - 5PM
- 8 hrs per day
- 5 days per week
- Tasks set to as soon as possible
- Resourcing set to 100% for all tasks
Anyone able to see what's going on?
First post ...
Using MS Project 2016
When I enter single day tasks (forecasted) they split across 2 days. On further investigation, it's because MSP changes the start time for these tasks to irregular times, such as 11:12 AM, then the 1 day task spans across 2-days.
Weird thing is; when you status the program - it often corrects to what it should be. . .
Checks I've done to try fix it:
- Calendar is 8AM - 5PM, no work 12:00 - 13:00 (lunch)
- Project Settings is 8AM - 5PM
- 8 hrs per day
- 5 days per week
- Tasks set to as soon as possible
- Resourcing set to 100% for all tasks
Anyone able to see what's going on?