Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Task predecessor based on day of week

Status
Not open for further replies.

tquinn

Electrical
Feb 18, 2005
2
US
I have 2 task A,B. Task A is a random day that is usually forced on me one way or another. Task B is always the 1st Tuesday after Task A. Is there a way I can set up the predecessor for Task B to be the proper Tuesday date? Thanks.
 
Replies continue below

Recommended for you

Figured it out. I just made a custom calender that stated Tuesdays were the only working days and then assigned taht to the meeting task.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Top