Lutfi
Structural
- Oct 20, 2002
- 1,036
I have a question, lets say I have a site with K = 250 PCI, then compact the soil to 98% up to 12 deep, then on top of that I place 8 inches of lime rock compacted to LBR 100. What would the new K value be? Or does it stay the same?