chella123
Structural
- Mar 29, 2007
- 1
I have a situation here where in contractor has poured the footings by draining the water in the pit. However, water table is 3'-0" above the bottom of the footing.
This was not brought to my notice. However, When i formed the core test at 21 days the compressive strength achieved was only 50% of the actual strength. Is there any method to strengthen the footing or should I ask them to demolice and re-do the footing?
Charles
This was not brought to my notice. However, When i formed the core test at 21 days the compressive strength achieved was only 50% of the actual strength. Is there any method to strengthen the footing or should I ask them to demolice and re-do the footing?
Charles