baterboy
Civil/Environmental
- Mar 25, 2015
- 5
Our industrial client has a large cistern no longer in use that he wants filled with stone and a new concrete top constructed. The cistern is 18' in diameter and 40' deep with a steel beam and concrete top. The beams have deteriorated and the concrete is failing. The walls are brick and stone in reasonable condition. Ground water fills the cistern to a height of about 25'. The cistern is in line with a truck dock and the concrete top must sustain tractor trailer loads.
We are proposing to remove the existing concrete top and beams and pump out the cistern. We would then install 10' of #4 stone and 20' of 3/4" stone followed by tamping with a boom mounted vibratory compactor. From prior pumping of the cistern ground water refills to the 25' level in about one week. We would stop at the 30' level to construct two concrete walls about 6' wide by 6' high closing two vision holes from a tunnel adjacent to the cistern. Once the walls are completed we would continue with the 3/4 inch stone fill and boom compactor to the top. We would then anticipate constructing a concrete slab on grade over the cistern fill and walls.
We would appreciate any comments regarding the fill process and possible settlement due to our proposed stone filling technique.
We are proposing to remove the existing concrete top and beams and pump out the cistern. We would then install 10' of #4 stone and 20' of 3/4" stone followed by tamping with a boom mounted vibratory compactor. From prior pumping of the cistern ground water refills to the 25' level in about one week. We would stop at the 30' level to construct two concrete walls about 6' wide by 6' high closing two vision holes from a tunnel adjacent to the cistern. Once the walls are completed we would continue with the 3/4 inch stone fill and boom compactor to the top. We would then anticipate constructing a concrete slab on grade over the cistern fill and walls.
We would appreciate any comments regarding the fill process and possible settlement due to our proposed stone filling technique.