ahunt
Structural
- Sep 10, 2005
- 44
Good Afternoon!
I have a project that requires steel bar joists supported off light gauge metal framing. This is the first project I’ve done this one. I’m expecting end uplift reactions of roughly 850 lbs. Anyone have suggestions on how to make this transition down to the metal stud?
I have a project that requires steel bar joists supported off light gauge metal framing. This is the first project I’ve done this one. I’m expecting end uplift reactions of roughly 850 lbs. Anyone have suggestions on how to make this transition down to the metal stud?