gmeadows
Civil/Environmental
- Feb 10, 2005
- 1
Hello,
I have around 30 tasks. I have assigned a WBS for each task. I first sort by WBS. Next I insert a blank task above a group of WBS items (could be around 5 tasks). Finally, I select each task in this group and indent the group. Weird behaviour occurs. Try it you'll see.
Any ideas on how to get this to behave correctly?
Thanks in advance.
glenn
I have around 30 tasks. I have assigned a WBS for each task. I first sort by WBS. Next I insert a blank task above a group of WBS items (could be around 5 tasks). Finally, I select each task in this group and indent the group. Weird behaviour occurs. Try it you'll see.
Any ideas on how to get this to behave correctly?
Thanks in advance.
glenn