HamidEle
Electrical
- Feb 20, 2007
- 309
have a question. We purchased a generator with a switchgear ( 4160V ), with two supplies, one is from Utility, the other is from 2x2.5MW generators. The utility is stepped down from 115KV transmission line. Under normal conditions, the generators will be standby. We will need to turn on the generators for periodic testing and maintenance, running in parallel with the grid ( no tie breaker). The sizes of the generators are small compared with the grid capacity. Wonder if we need to file an application to the grid for approval in this case. Is there any way we can get away from going to utility company for approval? Cause it would be a pain to go through all of these in the middle of commissioning the plant. Thanks in advance!