Has any of you ever placed a cantiler mast arm signal pole within the span of a bridge? The signal designer on a project that I am working on is pushing for this.
I feel that inducing approximately 240kip-ft into the deck and Bulb-T beams is unreasonable.
This is complicated by the fact that the pole will be placed in a location where it may be impacted by vehicles, which would increase the forces that the deck would need to resist.
Any comments or thoughts?
I feel that inducing approximately 240kip-ft into the deck and Bulb-T beams is unreasonable.
This is complicated by the fact that the pole will be placed in a location where it may be impacted by vehicles, which would increase the forces that the deck would need to resist.
Any comments or thoughts?