X-Wing
Civil/Environmental
- Sep 26, 2012
- 71
Hi everyone! I am designing for this certain project, and the plan needed/suggested to have an anchor deadman. I was given a force per linear meter of wall that the anchor will be restraining, and then I designed the deadman, the waler, the tie rods, and the plate.
My main question is the tie rods, because what came out from my design is that a 50mm tie rod is needed per deadman anchor, that was placed every 3.2m. To reduce the size, I instead use two tie rods, so I came up with 2-25mm. Is the tie rod diameter too big? considering the spacing of only 3.2m (for the deadman) and a unsupported depth of 5.5 meters of sheet piles (including the scour depth)? the length of piles is 12m each.
My main question is the tie rods, because what came out from my design is that a 50mm tie rod is needed per deadman anchor, that was placed every 3.2m. To reduce the size, I instead use two tie rods, so I came up with 2-25mm. Is the tie rod diameter too big? considering the spacing of only 3.2m (for the deadman) and a unsupported depth of 5.5 meters of sheet piles (including the scour depth)? the length of piles is 12m each.