jimtheengineer10
Civil/Environmental
Attached is a plan so you can see what I am talking about. I am reviewing some plans and the contractor has told the owner that it is a bad idea to have such short studs (approximately 16") under the lvl beam. Is this true? Is the lvl beam really necessary or can the rafters be attached to the side of the 2x6 studs?
Does the double 2x12 beam need to carry the floor load and two roofs loads (one from the upper roof and one from the lower roof)? The double 2x12 does not have a support wall underneath it all the way. It clear spans about 11.5'.
Thank you.
Does the double 2x12 beam need to carry the floor load and two roofs loads (one from the upper roof and one from the lower roof)? The double 2x12 does not have a support wall underneath it all the way. It clear spans about 11.5'.
Thank you.