On a composite slab the contractor welded the studs to the edge of the flange rather than the center of the beam. Moreover he poured the slab before we looked at it. My question is, now since the studs are welded off center will this reduce the capacity of my composite beam and is it written somewhere that the studs must be welded to the center of the beam?