we have a project that has a differential settlement limit of <15mm. Now the founds will be a mixture of piled unpiled. The si is pretty poor, with only boreholes supplied. Regardles of the poor si would you be comfortable working to tolerances of 15mm? I would think that this is to tight a margin to be able to determine.