KimWT
Structural
- Jul 15, 2003
- 71
Hi,
When you use self-compacting concrete, don't you need to be concerned about aggregate segregation problem
unless it is extreme case like using vibrator severely.
A salesman from admixture company explained about SCC use in precast concrete industry.
He did not mention about aggregate segregation at all, but air pocket or bug hole problem.
For example, when I pour SCC to produce 60ft long precast double tees of 28" tall stems and 4" thick flange,
what sequence of concrete placement should I follow:
1)do I pour stems and flange together? Make concrete mix truck pass once. Or
2)do I pour one stem first and then pour other stem and flange later. What time interval is good? Or
3)Can I pour SCC with mix truck stationed at one location and let it flow to everywhere? Or
4)Should I pour a part of stem and wait until internally entrapped bubbles can escape and pour remained portion later?
(Because 28" is too deep for the internal air to move to the top.)
Otherwise, it depends on which specific chemical is used.
I saw an European guideline say "NO GENERAL RULE."
So, aren't there generally accepted rules on concrete flow (max) distance or maximum hydraulic head?
Thanks for your time!
When you use self-compacting concrete, don't you need to be concerned about aggregate segregation problem
unless it is extreme case like using vibrator severely.
A salesman from admixture company explained about SCC use in precast concrete industry.
He did not mention about aggregate segregation at all, but air pocket or bug hole problem.
For example, when I pour SCC to produce 60ft long precast double tees of 28" tall stems and 4" thick flange,
what sequence of concrete placement should I follow:
1)do I pour stems and flange together? Make concrete mix truck pass once. Or
2)do I pour one stem first and then pour other stem and flange later. What time interval is good? Or
3)Can I pour SCC with mix truck stationed at one location and let it flow to everywhere? Or
4)Should I pour a part of stem and wait until internally entrapped bubbles can escape and pour remained portion later?
(Because 28" is too deep for the internal air to move to the top.)
Otherwise, it depends on which specific chemical is used.
I saw an European guideline say "NO GENERAL RULE."
So, aren't there generally accepted rules on concrete flow (max) distance or maximum hydraulic head?
Thanks for your time!