A recent article I had gone through about concrete cubes specifies
Sampling Rate /Quantity of concrete to be represented by each sample
Column, Shear Wall -- 10 cum
Solid Raft, Pile Caps and mass concrete -- 100 cum
All other type or parts --- 25 cum
From each sample of concrete taken 2 cubes shall be made
please comment
Thank you all
Sampling Rate /Quantity of concrete to be represented by each sample
Column, Shear Wall -- 10 cum
Solid Raft, Pile Caps and mass concrete -- 100 cum
All other type or parts --- 25 cum
From each sample of concrete taken 2 cubes shall be made
please comment
Thank you all