Hey yall, I've got a project where the roadway has settled where the water mains run perpendicular under the road. I did some research and found that the road has some organics deep in the subgrade, however, a couple years ago the subgrade was injection cemented. The utility pipes are laid with granular coarse aggregate material and the raod is still failing at these locations. We are set to repair these roads, any suggestions? I am yet to see what the existing conditions are, and will witnees when they cut out the road at these locations.