As you are using sand fill (dredged sand), settlements will occur rather quickly, like Ron implied, with the placement of the upper layers. You didn't say if the 5 m of fill was being placed above existing grade or dig out and replace scenario.
A couple of things - make sure you have some drainage provisions - the dredged sand will be wet and will want to drain when placed unless it has "lost" its moisture during transport, etc.
Secondly, and assuming that the placed fills are wholly or partly above the existing ground, the outer perimeters of the dredged sand layers need to be of a material that will help confine the dredged sand if the sand has a potential to "run". I have seen "clay' being used but the problem with this, unless you have some drainage holes through it, that the clay will act making the structure act as a bathtub which raises the groundwater level within the fills. I had wanted to use prefabricated wick drains laid horizontally to act as rainwater infiltration outlets through the clay confining zone but client and engineer didn't see the need. Time will tell, I guess.
On compaction, with dredged sand, think of checking the compaction of the previous lift rather than the lift you are placing as an acceptance criterion.
Another "toy" that might be considered is to mix in a couple of percent cement in the compacted sand layer - to increase the strength for the heavy loads. Mixing it with sand and a farm harrow is easily done as we did with a mix of fly ash and sand.