Dear All,
We have a 6" PSV (Set 55 KG/cm2, @ 220 Deg. C) Service is Ethylene glycol + water. The relief discharge is injected to a closing system 25 m away from relief point. We encountered a hammering when this PSV opens. An Idea was raised to elongate the relief line to about 60 m long and injected to a very low pressure line.
Can you please help to solve this problem. What is the best proffesional check list i must confirm to know what cause this problem.
Regards
SHARQ
We have a 6" PSV (Set 55 KG/cm2, @ 220 Deg. C) Service is Ethylene glycol + water. The relief discharge is injected to a closing system 25 m away from relief point. We encountered a hammering when this PSV opens. An Idea was raised to elongate the relief line to about 60 m long and injected to a very low pressure line.
Can you please help to solve this problem. What is the best proffesional check list i must confirm to know what cause this problem.
Regards
SHARQ