LakeNormanTiger
Civil/Environmental
- Feb 10, 2004
- 18
Friends,
I am a utilities precast engineer that usually deals with slabs and wall thickness that are 10" or less.
A project that we have been chasing requires 12" thick walls and a 16" base slab that will be monolythcally poured.
Original Design calls for one layer of steel in the center of the walls and the slab. Original design was rejected because it violates ACI-318. Basically telling me that because my slab is greater than 10" thick two matts of reinformement are required. I figured I was wrong and needed to reread the section, but I have not found anything in either section 7 or 10 regarding this. I still think the other guy is right, but could someone point me in the right direction.
Thanks
LNT
I am a utilities precast engineer that usually deals with slabs and wall thickness that are 10" or less.
A project that we have been chasing requires 12" thick walls and a 16" base slab that will be monolythcally poured.
Original Design calls for one layer of steel in the center of the walls and the slab. Original design was rejected because it violates ACI-318. Basically telling me that because my slab is greater than 10" thick two matts of reinformement are required. I figured I was wrong and needed to reread the section, but I have not found anything in either section 7 or 10 regarding this. I still think the other guy is right, but could someone point me in the right direction.
Thanks
LNT