Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Ram concept - AS 3600.2009 Load combo for initial service stage.

Status
Not open for further replies.

ramconcept-rapt

Structural
Joined
Jan 6, 2018
Messages
5
Location
AU
Ram concept - AS 3600.2009
Hi everyone, When I first looked into load combination of AS.3600-2009 for prestressed concrete, the initial service load combo in Standard is 0.9SW + 1.15P, which is different from 0.8SW + 1.15P in Ramconcept manual. Can anyone explained me why?
 
The manual, or at least this section, probably hasn't been updated recently. The factor used to be 0.8.
 
Thank you guys so much. That's me who asked the same question the other day with Bentley support.
 