"jump system" during bridge building ?

Status
Not open for further replies.

rb1957

Aerospace
Joined
Apr 15, 2005
Messages
16,133
Location
CA

at 1minute mark, the commentator says "jump system removed" (as part of progress made). Is this some temporary support used during building (and now things have advanced enough that it can support it's own weight it is no longer needed) ?

"Hoffen wir mal, dass alles gut geht !"
General Paulus, Nov 1942, outside Stalingrad after the launch of Operation Uranus.
 
The construction of concrete tower legs to cable stayed bridges typically uses a climbing/jump formwork system. Maybe he is referring to that.
 
yeah, makes sense, he went on to say "from the top of the tower"

"Hoffen wir mal, dass alles gut geht !"
General Paulus, Nov 1942, outside Stalingrad after the launch of Operation Uranus.
 