I have two pumps operating in separate sumps and joining at tee and entering a tank through a single line. All lines are 2" O.D. HDPE SDR 11 pipe, shortly after the connection, the line enters a manhole and exits as a 4" SDR 11 HDPE Pipe. I have very little info on the pumps other than one was spec'ed at 55 GPM at 96' TDH and the other at 53 GPM at 85' TDH. I need to ensure this configuration is not a problem, especially in the 2" line before it expands to 4". Any insight on how to best check this? Thanks.