Bottle
Mechanical
- Jan 25, 2008
- 5
Possibly a very stupid question, but I am looling for some opinions.
A section of pipework is due to be pressure tested according to ASME B31.1, and there are 2 flanged valves not yet installed as they have not been delivered.
How would one define the limits of the pressure test for the above example. Is it of the piping only, or should it include all equipment which would be normally installed (other than those which may be damaged by the pressure test)? What section of B31.1 defines the scope?
If 2 dummy/spacers were installed for the test would this suffice?
Should the contractor wait for the valves to be installed before carrying out the test?
Thanks in advance for any opinions offered.
A section of pipework is due to be pressure tested according to ASME B31.1, and there are 2 flanged valves not yet installed as they have not been delivered.
How would one define the limits of the pressure test for the above example. Is it of the piping only, or should it include all equipment which would be normally installed (other than those which may be damaged by the pressure test)? What section of B31.1 defines the scope?
If 2 dummy/spacers were installed for the test would this suffice?
Should the contractor wait for the valves to be installed before carrying out the test?
Thanks in advance for any opinions offered.