When is the splice ring installed? I saw no mention of this in the question.
If you are installing a splice ring, you could use a CJP weld. However, B-U4a as do the other welds require a "gap" or root opening between the two materials. The root opening varies with the prep angle, but is usually about 1/4" (+1/16"/-0")for a 45(+10 degree/-0 degree) degrees or 3/8" (+1/16"/-0")for a 60 (+10/-0) degree angle. These root opening dimensions are as detailed. Knowing what field conditions are, you are allowed to deviate from the root opening dimensions, usually by +1/4" or -1/16". The deviation from the detailed dimension is refered to as "Fit-up". Assuming a 45 degree angle, the root opening may vary between 3/16" to 9/16" and the angle can vary from 40 degrees to 65 degrees. Regardless, what the angle is , you still need to provide a root opening.
Now the fun part......how do you "hold" the pile in place and still maintain the opening while the welder is welding the pile?
It is an expensive process to have a welder or multiple welders on site waiting to weld installed piles. Try using shorter pile with the splicer, it might be less expensive in the long run.