Thank you all for your inputs. The reason I was looking for the Vecotr Groups is that I'm facing a proplem in my work. We have built a new Centeral Control Room that shall be feed through new substation. The new substation (S/S M) is a duble ended, with two feeders from two different sources and a normaly open bus tie. The first source, (Incomer A) is from bus # 400 13.8KV through DY1 transformer (13.8/6.3KV) to S/S 100B, then from S/S 100B to S/S M through DY11 transformer (6.3/0.4KV)The second feeder (Incomer B) is from bus # 300 13.8KV to (S/S N)through (13.8/0.4KV) DY1 transformer.
Now, due to the difference in the Transformers vecotr groups, is it possible to parell the two incomers without having any problem? if not, what is the most preactical soultion to such problem?