lmacallndong
Specifier/Regulator
- Feb 25, 2012
- 14
I am checking a Compress calculation report and the designer modeled a 50 ft seam/seam tower with just a single shell course instead of multiple shell course, e.g. 5 shell cans that are 10 ft long.
Will the period of vibration be the same?
Will the period of vibration be the same?