Hello,

I would like to know if anyone knows a method to estimate the piping material in project in the preliminary phase, with the P&IDs and simple Layouts. Could you recomend me some bibliography?

Thanks in advance.
 
Replies continue below

Recommended for you

You really should specify fluid and flow rate in a question like that. If you are talking about a million barrels a day of sea water you are in a different set of materials than if you're talking about 2 MCF/day of sweet natural gas.


David Simpson, PE
MuleShoe Engineering

"Belief" is the acceptance of an hypotheses in the absence of data.
"Prejudice" is having an opinion not supported by the preponderance of the data.
"Knowledge" is only found through the accumulation and analysis of data.
 