I have a concrete beam with 200mm width and pipe sleeve of diam 50mm shall go through this beam vertically
- Reinforcement for this beam is 2 dia 16 , so as per code ACI318 i have to achieve cover 40 mm to stirrups and 20 mm to main RFT, for that purpose all my beams in the project shall be increased in width and it is not accepted at all.
anyone have a solution for this case?!!
I have a concrete beam with 200mm width and pipe sleeve of diam 50mm shall go through this beam vertically
- Reinforcement for this beam is 2 dia 16 , so as per code ACI318 i have to achieve cover 40 mm to stirrups and 20 mm to main RFT, for that purpose all my beams in the project shall be increased in width and it is not accepted at all.
anyone have a solution for this case?!!