bones206 said:
1) I have a soil boring that shows bouldery, gravelly silt conditions...
...I’m sure the bouldery soil would preclude them anyways.
2) I suspect that the noise and vibration of driven piles could open a political can of worms...
...without high levels of noise and vibration that the local residents will tolerate?...
1) If conditions are as bad as you assume... doubt a typical boring could have been made. Maybe a few question about the field details encountered during the boring would shed more light on soil conditions.
2) I disagree with using "noise level" as the primary criteria to dictate design. As a former bridge contractor, sometime driving piling in residential areas, I can tell you first-hand that "noise" is only one factor... probably NOT the most important one, either.
Time of day for the "noise" is important. Say 9am to 5pm, as apposed to sunup to sundown.
Which days of the week, too. Monday thru Friday, ok. Weekends, no.
The most important is
duration of the work. If the Contractor gets "in" and "out" on schedule - great. The worst is to have work "drag" on for what seems like a long, long time.
If driven pile are "best" (IMHO, probably are considering the description), there are steps that can be taken to minimize pile driving noise. You will have to work with a qualified pile driver to determine the details, but the following is possible:
A. Select a type pile hammer that is optimum for the piling and condition.
B. Within that type hammer, select one with optimum energy rating AND geometry.
As an example, say that a single-acting impact hammer is determined to be best. Also, an energy rating of 22,000 to 25,000 foot-pounds is optimum. Then, select, perhaps, a Vulcan 0 (24,400 ft-lb) versus a MKT DE-30 (22,400 ft-lb). The deciding factor (to reduce noise) is the impact velocity of the ram on the anvil (pile). A Vulcan 0 has a 7500 lb ram falling 39 inches. The MKT DE-30, 2800 lb, ram falling 96 inches. Lower impact velocity for the Vulcan.
The lower the impact velocity the more efficient energy is transferred from the ram to the pile... more efficient, less noise.
Use a proper size hammer... more efficient advancing the pile rather than "bouncing" the pile of the rock and rebounding the ram... advance the pile, less noise.
The funny thing is, with this level of attention to detail, the pile driving (if it is appropriate for this project) will go more smoothly, quickly, (relatively) quietly and cost effectively.
If you do decide to go with driven piling, after the pile driver has mobilized, have them drive a few "index piling" to determine if the proper hammer has been selected... sort of a DIY geotechnical investigation for a pile driver.
![[r2d2] [r2d2] [r2d2]](/data/assets/smilies/r2d2.gif)