jike
Structural
- Oct 9, 2000
- 2,160
For a typical 3 span gable roof PEMB frame, what are the designer's assumptions: The interior pipe columns pinned top and bottom and all the lateral load carried by the exterior tapered columns? or all columns (interior and exterior) work together to resist lateral loads in frame action?